Narrative Description of the Project

The Anukulan/ BRACED is a UKAID funded project to build the resilience of half a million poor and vulnerable people. The resilience being built, especially of women and children, is against climate change impacts like floods, landslides, and drought.

SAPPROS Nepal is a consortium partner and leads the water resource component and Enterprise Development component in all of the six project districts. In addition to leading the two components in all project districts, SAPPROS is leading the overall programme implementation in Doti and Dadeldhura districts.

Objective of the Project

  • Increase the annual income for 100,000 households (30000 direct HH, 70000 Value chain HH) (benefiting over 500,000 people) by £140 per month.
  • Promote the integration of DRR and Climate Change Adaptation measures.
  • Reduce the proportion of children, under the age of five, suffering from malnutrition.
  • Empower women, as measured by the WEAI, to take leading roles in rural institutions contributing to economic opportunities.

 BRACED Progress – April, 2017

Activity code Activities Project Target Total
Achievement Progress%
1.11.1 Technical capacity building training to Staff 1 1 100
1.11.2 Procurement of Survey equipment 4 4 100
1.11.3 Procurement of MUS forma 4 4 100
1.11.4 Pre-feasibility survey 184 141 77
1.11.5 Water quality testing 4 4 100
1.11.6 Detailed feasibility and Engineering survey 162 126 78
1.11.7 MUS registration/ Agreement (including Solar) 162 120 74
1.11.8 User group formation and orientation (including solar) 162 111 69
1.11.9 Gravity MUS installation 152 110 72
1.11.10 WUC training on planning and operation 162 122 75
1.11.11 Caretaker on the job training 162 124 77
1.11.12 MUS training/orientation to DTOs 4 4 100
1.11.13 Solar MUS installation through Anukulan 7 50
1.11.14 Solar MUS installation through Solar MUS II 3 50
1.12 Development of Recharge Ponds 60 60 100
1.13.1 Water source protection trainings 162 130 80
1.13.2 Catchment improvement works 162 131 81
1.21 MIT promotion 22000 17097 78
1.22 Mistri training 18 18 100
1.23 Farmers MIT repair and maintenance training 470 364 77
1.24 MIT (Drip) demonstration (90 sq. meter) 200 144 72

 

Project Duration  :
January 2015 to December 2017

Funding Agency    :
UKAID/iDE

Funding Amount  :
NPR 117,092,272 (UK£ 791,164)

Beneficiary HH     :
100,000

Project Area           :
Doti, Dadeldhura, Kanchanpur, Kailali, Bardiya and Surkhet